Belmont View Development Update

At week 22 of the 37 week build programme, block A, the 5 bed front extension is now watertight, with the new tile roof complete and the first fix mechanical and electrical works on going. [[{"type":"media","view_mode":"media_large","fid":"1714","attributes":{"class":"media-image aligncenter size-full wp-image-4601","typeof":"foaf:Image","style":"","title":"122","alt":""}}]] Block B, the 2 storey 20 bed rear extension, is now watertight and roof tiling will be completed this week, with first fix mechanical works in progress. The Quantum Care team is finalising the choices of finishes, fixtures and fittings in partnership with a professional design team. [[{"type":"media","view_mode":"media_large","fid":"1715","attributes":{"class":"media-image aligncenter size-full wp-image-4603","typeof":"foaf:Image","style":"","title":"127","alt":""}}]]