Newhaven Development Update

We are at week 38 of the build programme and the roof trusses have been installed on one wing of the building, with felting & battening being complete on this section by 21 October 2011. Roof truss installation is continuing along the central area, and into the other wing, which will leave the whole building watertight within the next month. [[{"type":"media","view_mode":"media_large","fid":"1729","attributes":{"class":"media-image aligncenter size-full wp-image-4783","typeof":"foaf:Image","style":"","title":"P1070471","alt":""}}]] Windows have been installed throughout the ground and first floors, with the second floor following over the next 2 weeks. External rendering will then start and it will be possible to see the overall effect of the building. [[{"type":"media","view_mode":"media_large","fid":"1730","attributes":{"class":"media-image aligncenter size-full wp-image-4784","typeof":"foaf:Image","style":"","title":"P1070478","alt":""}}]] [[{"type":"media","view_mode":"media_large","fid":"1731","attributes":{"class":"media-image aligncenter size-full wp-image-4785","typeof":"foaf:Image","style":"","title":"P1070482","alt":""}}]]