Stevenage Development

Work continues on our new home in Stevenage. It's a 90 bedded home and is being constructed by GB Building Solutions. The work began in January 2011 and is predicted to be completed in May/June 2012. To date, the piling and ground works are complete. The steel works holding up the first floor are in place and the masonry is up to the first floor. [[{"type":"media","view_mode":"media_large","fid":"1703","attributes":{"class":"media-image aligncenter size-full wp-image-4332","typeof":"foaf:Image","style":"","title":"Stevenage Development Site","alt":"Stevenage Development Site"}}]] [[{"type":"media","view_mode":"media_large","fid":"1704","attributes":{"class":"media-image aligncenter size-full wp-image-4333","typeof":"foaf:Image","style":"","title":"Stevenage Development","alt":"Stevenage Development"}}]]