Trefoil House Development Update

The build at Trefoil House is now entering the final stages, with the Show Rooms being fully completed, fitted out and opened at the beginning of September. The emphasis of our contractors and partners, Castleoak, has now changed and specialist finishing managers have been brought in to work with our project team to ensure a quality end product. Internally, decoration and carpeting are nearing completion. Externally the car park and entrance road are also almost finished. The mechanical and electrical installations have been largely commissioned and are fully operational, including the new Combined Heat and Power unit, helping to ensure Trefoil House is our most fuel efficient Home. The Home has also been air pressure tested and has scored highly, contributing further to its efficiency. The completion and handover date for the whole of the project is 29th October, ahead of the contracted date.