Willow Court Development Update

Works have progressed well through week 13 of the 42 week project, with Phase 1 of the external works complete, the temporary access to the rear of the site installed and timber frame to the rear extension erected. [[{"type":"media","view_mode":"media_large","fid":"1733","attributes":{"class":"media-image aligncenter size-full wp-image-4793","typeof":"foaf:Image","style":"","title":"P1070324","alt":""}}]] The coming weeks will see brickwork and roofing progressing externally, followed by first fix mechanical and electrical and plaster boarding internally. [[{"type":"media","view_mode":"media_large","fid":"1734","attributes":{"class":"media-image aligncenter size-full wp-image-4794","typeof":"foaf:Image","style":"","title":"2011-10-20-13.00.19","alt":""}}]] The Best Friend’s Café has been completed by the Quantum Care Facilities Management Team and the new mini bus has been procured. [[{"type":"media","view_mode":"media_large","fid":"1735","attributes":{"class":"media-image aligncenter size-full wp-image-4795","typeof":"foaf:Image","style":"","title":"2011-10-20-13.00.57","alt":""}}]]